Logistics and materials management

The operation of storage facilities linked to offshore pipeline construction projects involves the coordination of the inward and outward flow of pipes, combined with quality assurance procedures which ensure that pipes with correct specifications, wall and Concrete Weight Coating (CWC) thickness, are loaded onto the correct vessel for punctual delivery to the lay barge.


Marshalling yard operations carried out by NorSea Group facilitate the maximum utilisation of available storage areas. The exclusion of access roads between pipe stacks, combined with planning to ensure optimum availability of the correct pipe qualities in the right sequences are our top priorities. This ensures efficient equipment fleet operation under very tight schedules, with minimum downtime and sufficient availability of spares.